New leisure centre hit by delays after subcontractor entered administration

News | Nicholas Thomas - Local Democracy Reporting Service | Published: 16:05, Wednesday November 6th, 2024.
Last updated: 16:05, Wednesday November 6th, 2024

Support quality, independent, local journalism…that matters

From just £1 a month you can help fund our work – and use our website without adverts. Become a member today

An artist's impression of how Caerphilly's new leisure centre could look
An artist’s impression of how Caerphilly’s new leisure centre could look

Caerphilly’s new leisure centre could be delayed by four or five months after building firm ISG went into administration.

Caerphilly County Borough Council’s regeneration committee was told, on Tuesday October 5, that the local authority did not have any direct contracts with ISG, but the firm had been subcontracted to work on the town’s leisure centre project.

ISG entered administration on September 20 and its UK operations ceased to trade with immediate effect.

“No further work will be undertaken on existing UK contracts, including for construction, fit out and engineering services,” the firm’s administrators said in a joint statement published on the ISG website.

Ahead of the Caerphilly Council committee meeting, a report stated the tender for the build of the £33.6m leisure centre project, at Caerphilly Business Park, had been “awarded to ISG”.

The location of the proposed new leisure centre
The location of the proposed new leisure centre

“However, they subsequently went into administration requiring the project to go back out to tender”, according to the report, which added that £12.2m of the project’s budget, which had been allocated for the current financial year, “is now forecast to be slipped into 2025/26 due to this delay”.

Cllr Gary Enright asked whether the council would be able to recoup any money it had spent on the deal.

But he was told the council had “never had a contractual relationship with ISG” for the project and hadn’t “paid anything” to the firm.

Instead, the council’s contractor for the leisure centre is Alliance Leisure, which in turn had subcontracted ISG for some work, the committee heard.

However, ISG entering administration had “left quite a void” in the project, which is “probably looking at a four to five month delay” while a new subcontractor was found, an officer told Cllr Enright.

Corporate director Richard Edmunds told the committee the council had done its “due diligence”.

Liz Lucas, the council’s head of customer and digital services, added that Caerphilly Council had followed a “pre-established” procurement system for the leisure centre contract.

“As soon as we knew there was a problem… we acted very quickly,” she said, adding: “Due diligence was done and will continue to be done.”

The new “leisure and wellbeing hub” will replace the town’s existing sports facilities at Virginia Park, which have been deemed “dated” and “not considered viable” to keep open.

Work to build Caerphilly’s new leisure centre set to begin next summer

Sign-up to our daily newsletter


Support quality, independent, local journalism…that matters

From just £1 a month you can help fund our work – and use our website without adverts.

Become a member today

Watson Batty Architects
Watson Batty Architects
Google/LDRS

Latest News

  • An artist’s impression of one of the new displays in Blackwood
    Town-centre display boards approved despite brightness concernsFriday, January 9, 2026
  • Welsh Labour pledges £2 bus fare cap in Senedd election manifestoFriday, January 9, 2026
  • Old Club, Bailey Street, Deri, pictured in July 2025
    Support for conversion of former club into family homeFriday, January 9, 2026
  • Mark Lawton, managing director at Harlech Food Service
    Food wholesaler smashes sales records with £30m increaseFriday, January 9, 2026
  • 115 High Street (on the right), Blackwood, pictured in June 2025
    Green light for new pool, darts and coffee shop proposal on town’s high streetFriday, January 9, 2026
  • Gwent Police officer
    Police relationship with schools ‘better’ since liaison officer funding axedFriday, January 9, 2026

Find out how the communities of Caerphilly County Borough get their names

Caerphilly

Legal & Public Notices

  • Caerphilly County Borough Council public noticesThursday, January 8, 2026
  • Caerphilly County Borough Council public noticesThursday, December 11, 2025
  • Caerphilly County Borough Council public noticesThursday, November 27, 2025
  • Notice of application for a premises licence: Darts Dungeon, BargoedThursday, November 27, 2025
© 2009-2024 Caerphilly Media Ltd, Caerphilly Miners Centre for the Community Watford Road Caerphilly, CF83 1BJ. Incorporated in Wales No. 07604006.