A target completion date for work on the Pwllypant roundabout has been reached between Caerphilly County Borough Council and its main contractor.
The major project is anticipated to be completed before Christmas, if works progress to plan.
The project was originally due to be completed by October, but was revised following key changes to the contract, including the re-opening of two lanes of traffic on the roundabout from the Llanbradach bypass.
Cllr Sean Morgan, Deputy Leader of Council said: “We are aware of the importance of completing these works as quickly as possible, particularly before the Christmas period which is key for local businesses.
“We assure all concerned that any work to finalise the programme during December will aim to have minimal disruption on the travelling public.
“The council has worked closely with our contractor to respond positively to the needs of residents and the local business community and we are pleased that the details of the completion of the programme have now been finalised up to this point.”
Cllr Morgan added a note of caution that “unforeseen circumstances could have an impact on our time frames.”
Nick Rolfe, Contract Director of Walters, the project’s main contractor, said: “The scheme has thrown up a number of difficult issues over the last few months and the project team, made up of both Walters and council staff, have responded with a positive and proactive approach, on what has become a challenging project.
“This has enabled us to optimise our resources and supply chain, the majority of which are based in the region, and improve on the planned completion date and lessen the overall impact on all stakeholders. We have some way to go but we are optimistic that we can complete before Christmas 2018.”
The council revealed earlier this week that the roundabout and its Llanbradach approach will return to a single lane from Monday, July 30 for a period of four to five weeks.