Caerphilly Observer
Member Sign in Manage Membership
Become a Member - no ads
Menu
  • News
    • Senedd
    • Business
    • Newport
    • Opinion
  • Sport
    • Rugby union
    • Football
  • Membership & Subscriptions
  • Notices
  • Advertise
  • About
  • Sponsored Content
Menu

Opposition Plaid Cymru councillors criticise Pwllypant roundabout work overspend

News | Niall Griffiths - Local Democracy Reporting Service | Published: 16:53, Friday December 28th, 2018.
Last updated: 17:01, Friday December 28th, 2018

The completed scheme took almost two months longer to complete than originally scheduled

Controversial works to improve Caerphilly’s Pwllypant roundabout have cost around £8 million to complete, it has been revealed.

Caerphilly County Borough Council say total costs rose by around £2.7 million – an increase of more than 50% on the project’s estimated cost of £5.3 million.

Work began in October 2017 and was due to finish within a year, but it was not completed until late November.

According to the council most of the extra cost came from reopening two lanes following concerns over disruption caused by single lane restrictions.

Breakdown of the total cost of the project:

• £2,967,350.02 – Welsh Government direct scheme grants (this includes grant funding for pre- construction costs)
• £700,000.00 – Indirect Welsh Government grants
• £4,238,512.12 – Section 106 contributions (funds from private developers)
• £210,792.19 – Caerphilly council funding

Plaid Cymru’s group leader on the council has criticised the Labour-led authority’s handling of the project, which was carried out by construction firm Walters.

“Some of the reasons quoted for the vast increase could be put down to a lack of foresight when the contract was first awarded,” said Councillor Colin Mann.

“The huge chaos caused by the work shouldn’t have come as a surprise, if proper traffic counts had been taken.

“Single lane travel did have a massive impact on travel times, particularly for commuters travelling to and from work.

“Businesses situated locally have quoted massive losses in takings which could seriously threaten their future viability.”

Figures obtained by Plaid show the original costs before tender included pre-construction design fees, surveys, ecological mitigation as well as construction costs and post scheme liabilities.

Cllr Mann added: “This scheme is important in helping reduce congestion for drivers’ travelling to and from the Rhymney Valley. However, in anyone’s language, this represents a massive increase in costs.”

The project also received significantly more grant funding from the Welsh Government than originally anticipated.

But the council is expecting the final cost for the construction contract with Walters to be around £5.5 million.

A council spokeswoman said: “The overall estimate has undoubtedly increased prior to tender, with much of the additional cost arising from [Walters] revising their method of working on the southbound Llanbradach arm.

“These alterations were made after listening to concerns from the public, local councillors and businesses about disruption they were experiencing with the single lane operation.

The spokeswoman continued: “The effects of moving from single lane working and unforeseen service diversions, two significant snowfalls and other eventualities beyond our control had a significant impact on the works programme.

“Despite this, the council and contractor worked extremely hard to mitigate any extension to the works programme, with the project being delivered only a few weeks over the original scheduled 12 months, and more importantly, prior to the busy pre-Christmas trading period which is crucial for local businesses.”

Leave a Reply Cancel reply

You must be logged in to post a comment.

Latest News

  • Labour chooses Richard Tunnicliffe as Caerphilly by-election candidateSaturday, September 6, 2025
  • HM Morgan Engineers is based in Trecenydd, Caerphilly
    ‘I don’t know what the future would have been’: Caerphilly firm turns around fortunesFriday, September 5, 2025
  • Caerphilly County Borough Council's headquarters in Tredomen
    Complaints about council in line with Welsh averageFriday, September 5, 2025
  • education
    Schools with ‘very high surpluses’ expected to justify unspent fundingFriday, September 5, 2025
  • Gerwyn Price is through to the second round of the World Matchplay
    Price to compete at Czech Darts Open after recovering from hand injuryFriday, September 5, 2025
  • Aber Valley Wolves launched its wheelchair rugby league section in March 2025
    ‘Absolutely anyone can play’: Strong start for inclusive wheelchair rugby league teamFriday, September 5, 2025

Find out how the communities of Caerphilly County Borough get their names

Caerphilly

Legal & Public Notices

  • Caerphilly County Borough Council public noticesThursday, September 4, 2025
  • Notice of application for a variation of a premises licence: St Cenydd Road, TrecenyddTuesday, September 2, 2025
  • Notice of application for a variation of a premises licence: Heol Aneurin, PenyrheolTuesday, September 2, 2025
  • Notice of application for a premises licence: Tredegar Street, RiscaSaturday, August 16, 2025
© 2009-2024 Caerphilly Media Ltd, Caerphilly Miners Centre for the Community Watford Road Caerphilly, CF83 1BJ. Incorporated in Wales No. 07604006.