‘Dreaded but persistent inflation’ drives up school rebuild costs

News | Nicholas Thomas - Local Democracy Reporting Service | Published: 16:25, Wednesday July 23rd, 2025.
Last updated: 16:25, Wednesday July 23rd, 2025

Support quality, independent, local journalism…that matters

From just £1 a month you can help fund our work – and use our website without adverts. Become a member today

Artist impression of the proposed replacement Plasyfelin Primary School, Caerphilly
Artist impression of the proposed replacement Plasyfelin Primary School, Caerphilly

“Dreaded but persistent inflation” is partly to blame after the budget of a Caerphilly school project increased by nearly £3 million.

The county borough council’s leader who made the remark, Cllr Sean Morgan, said inflation rises in construction were “certainly higher” than those faced by consumers.

The redevelopment of Plasyfelin Primary School, in Caerphilly town, was initially estimated to cost £20.48 million, but has now risen to £23.25 million.

Caerphilly County Borough Council, which is providing around a third of the overall funding for the rebuild, has seen its contribution increase by an extra £1.76 million.

Projected cost of new primary school rises by nearly £3m

The authority’s cabinet members approved the budget increase at a meeting on Wednesday July 23.

Cllr Carol Andrews, the cabinet member for education, said “further site investigations, design confirmations, and inflation in the construction sector” had all played a part in driving up the bill.

Cllr Carol Andrews, Labour councillor for the Gilfach ward
Cllr Carol Andrews, cabinet member for education and communities

Most of the council’s extra spending will come from an unallocated capital grant, while the remainder will come from a separate education capital fund.

The redevelopment of Plasyfelin Primary will begin this summer, and take place in phases – with some children learning in temporary classrooms during the construction period.

Cllr Jamie Pritchard, the council’s deputy leader, said the community was “very much in favour” of the project, which is taking place in his Morgan Jones ward.

Plasyfelin is being funded through the Sustainable Communities for Learning programme, and the Welsh Government will foot around two-thirds of the bill – as well as any contributions towards net-zero carbon elements of the project.

Andrea West, the council’s Sustainable Communities for Learning service manager, said the government had provided a “verbal approval they are happy to proceed” with the increased budget.

Cllr Morgan added the extra costs represented a “slight uplift to pay for a brand-new school”.

Summer break to bring major changes to some borough schools

Sign-up to our daily newsletter


Support quality, independent, local journalism…that matters

From just £1 a month you can help fund our work – and use our website without adverts.

Become a member today

The Urbanists
CCBC

Latest News

  • Caerphilly County Borough Council's headquarters in Tredomen
    Council leader seeks funding pledges from new Welsh GovernmentFriday, June 12, 2026
  • Calls for an end to term-time only pay for school support staffFriday, June 12, 2026
  • General view of M4 traffic at Newport
    Gridlock fears after minister takes M4 relief road ‘off the table’ and considers junction closuresFriday, June 12, 2026
  • Sioned Williams, Deputy First Minister and minister for social justice and equality
    Transgender people “feel under siege”Friday, June 12, 2026
  • Coronavirus vaccine
    Men B vaccine rollout announced following Kent outbreakFriday, June 12, 2026
  • Will Bishop, left, speaking with pupils at Trinity Fields School
    Pupils inspired by visit from gold-medal winning para-athleteFriday, June 12, 2026

Find out how the communities of Caerphilly County Borough get their names

Caerphilly

Legal & Public Notices

  • Notice of application for a premises licence: Cefn Fforest Miners Welfare HallFriday, June 12, 2026
  • Caerphilly County Borough Council public noticesThursday, June 11, 2026
  • Notice of application for a premises licence: Cross Oak Inn, OakdaleFriday, June 5, 2026
  • Caerphilly County Borough Council public noticesThursday, May 28, 2026
© 2009-2026 Caerphilly Media Ltd, Caerphilly Miners Centre for the Community Watford Road Caerphilly, CF83 1BJ. Incorporated in Wales No. 07604006.